The existing parking lot was experiencing high volumes of parent drop-off/pick-ups, which resulted in severe congestion and delays causing traffic to back-up onto the mainline roadway. Additionally, the existing parking lot only had one shared-use entrance for both staff/parents and buses, which further compounded traffic congestion. Provided designs to reduce congestion and improve peak traffic flow by separating bus traffic and staff/parent traffic. Designed a new vehicular entrance loop for buses/visitor parking only and expanded existing parking lot to accommodate all staff while concurrently redefining a drop-off location with sufficient queue length to not impact the adjacent road. The design was completed and regulatory permitting obtained within a strict 6-month time frame so construction could begin during the summer months.